





Project Name
Sunbury Water Treatment Plant Hydrotreater Rehabilitation
Location
Sunbury, PA
Project Description
The Sunbury Water Treatment Plant project consisted of removal of existing treatment equipment, modification to two (2) existing 56′ diameter concrete tanks, construction of a new clarifier control building, new sludge pumps and control system, installation of two (2) new clarifiers or hydrotreaters, construction and placement of two (2) new aluminum domes on each existing tank, various new sitework improvements including, but not limited to, new piping and outfall structure.
Gallons Per Day
3.5 MGD
Owner’s Name
Municipal Authority of the City of Sunbury
Engineer
Uni-Tec Consulting Engineers