Performance Construction was hired as a subcontractor to form, pour, and place the cast in place concrete. The scope of work included a 40 foot spillway with ogee weir. To the right of the spillway is the outlet structure. On each side there are
large embankments with mass concrete. Connected to the right embankment is the over 400 foot long Grade Control wall ending with an abutment. In addition to these structures, we form and poured two abutments and wing walls for a small pedestrian bridge. This project totaled over 2000 cubic yards of concrete.