Performance Construction Company was selected for the City of Pottsville’s FEMA Flood Repairs Project.
This project consisted of two separate locations within the city of Pottsville. Location number one was located on Peacock St and consisted of replacing 35 LF of collapsed stone archway. Location number two was located on Progress Avenue and consisted of replacing 250 LF of collapsed stone archway.
We had to tie into the original stone archway on the Progress Avenue site and maintain the waterflow. This road was closed for approximately 2 years prior to the approval of the funds from FEMA and was at one time a very heavily travelled roadway in the city.